Resale flat renovation: the order of works

The order of works for a resale flat is: inspection, design and quotes, permit, hacking and demolition, plumbing and electrical first fix, wet works, carpentry, painting, final fix, cleaning and a defects check. Each stage depends on the one before, so an early delay pushes back the rest.

Your resale HDB renovation timeline starts before any hacking. Use the resale flat inspection checklist to note what needs repair, such as old pipes, wiring or tiles, then ask each contractor to quote on the same scope.

Order of works for a resale flat
StageWhat happensWho
InspectionList what needs workYou
Design and quotesAgree layout, finishes and scope in writingYou and your DRC contractor
PermitApply for any HDB permit neededYour DRC contractor, for you
Hacking and demolitionRemove old finishes, fittings and any walls being taken outYour DRC contractor
Plumbing and electrical first fixRun new pipes and wiring routesLicensed workers via your contractor
Wet worksScreeding, waterproofing and tilingYour DRC contractor
CarpentryFit cabinets and wardrobesCarpenter
PaintingPaint walls and ceilingsPainter
Final fixFit lights, switches, taps and sanitary wareLicensed workers via your contractor
CleaningClear dust and debrisPost-renovation cleaners
Defects checkList items to fix before move-inYou, then your contractor

Plan your move-in date around the stage your contractor expects to take longest.

Permits first

Sort out the paperwork before any hacking starts. HDB says some renovations need an HDB permit, and those works must start only after the permit is granted. Works that need no permit must still follow HDB's guidelines, or they count as unauthorised works.

The application goes through your contractor. Under HDB's permit process, you authorise your DRC contractor to submit the renovation application on your behalf, using an acknowledgement form you sign.

DRC contractors know HDB's requirements, but HDB does not endorse or vouch for the quality of their works. Ask each contractor how they will handle the permit stage.

To see which works need a permit and how the process runs, read our guide to the HDB renovation permit. You can also check your plan item by item with the renovation permit checker.

Hacking and wet works

Hacking and demolition come first once the paperwork is in place. Your contractor removes old tiles, fittings, built-ins and any walls you plan to take out. Before you design a layout around removing a wall, read our guide to hacking walls in HDB flats and ask your contractor whether that wall can be hacked and whether it needs a permit.

Plumbing and electrical first fix follow hacking. New pipes and wiring routes go in before wet works, so finished tiles do not have to be broken later.

Wet works cover screeding, waterproofing and tiling. For bathrooms and toilets, HDB requires pre-packed waterproofing screed and a waterproofing membrane before new floor finishes are laid, with the membrane turned up at least 150mm against walls and kerbs. Replacing floor finishes needs an HDB permit.

Carpentry usually follows wet works, so cabinets and wardrobes are not fitted while floors and walls are still being tiled. Ask your contractor to check the waterproofing before the bathroom is tiled over.

Electrical and plumbing

If your inspection shows old wiring or pipes, decide early whether to replace them. The Energy Market Authority (EMA) says electrical work at home should be carried out or supervised by a Licensed Electrical Worker (LEW). EMA says electrical work in an HDB flat needs a Licensed Electrician, the class of LEW approved for loads of up to 45kVA. See EMA's page on engaging licensed workers.

Under HDB's electrical works guidelines, wiring must not be embedded in reinforced concrete slabs, beams, columns, walls or wall plaster; it is housed in metal or high-impact PVC conduit. New wiring can run behind carpentry, so agree the routes before carpentry starts. SP Services tests new wiring using Form CS/5H endorsed by HDB, applied for through your LEW.

PUB requires water service and sanitary plumbing works to be done by a PUB Licensed Plumber, except the listed simple plumbing works, such as replacing a tap or the flushing mechanism in a cistern, that a handyman may do.

NEXT STEP

See handyman companies in the directory with their published prices, the areas they say they cover and their sources.

Compare handymen

Keeping to schedule

Book trades in sequence. Each one needs the stage before it finished: tiling follows first fix, carpenters take final measurements after wet works, and painters follow carpentry. Ask your contractor for a written schedule that shows each stage and who coordinates the trades.

Check works hours with your neighbours in mind. Hacking and drilling are noisy, so read our guide to HDB renovation hours before you fix dates, and let your neighbours know what is coming.

Changes in the middle of the works add time, and the cost depends on the job. Agree any change in writing before it starts. Before day one, run through the pre-renovation checklist so the paperwork and site arrangements are sorted.

Questions

How long does a resale flat renovation usually take?

The length depends on the scope of works, so ask your contractor for a written schedule by stage. A repaint with minor repairs is far shorter than a full job with hacking, wet works and carpentry. Allow time for any permit HDB requires before works start, and for a defects check at the end.

Can I start renovating before key collection?

No. Works start after the sale completes and you have the keys, and work that needs an HDB permit starts only after HDB grants it. Before then, finalise the design, compare quotes and choose a contractor from HDB's Directory of Renovation Contractors.

When does rewiring fit into the renovation schedule?

Rewiring goes after hacking and before carpentry, painting and the final fix. EMA says electrical work in an HDB flat needs a Licensed Electrician, the class of LEW approved for loads of up to 45kVA. See EMA's page on engaging licensed workers. HDB does not allow new wiring to be embedded in walls or plaster, so agree the routes before carpentry.

Do I need to replace old water pipes?

Not always: ask your contractor to check their condition at the inspection stage. Any replacement goes after hacking and before wet works. Water service and sanitary plumbing works must be done by a PUB Licensed Plumber, except the simple plumbing works PUB lists that a handyman may do.

Can I stay in the flat during renovation?

You can for light works, but for a full renovation it is usually easier to stay elsewhere. Hacking and wet works bring dust and noise, and bathrooms may be out of use during waterproofing and tiling. If you need to stay, ask whether the works can be phased so one bathroom stays usable.

When should I book the movers?

Book them for a date after the final clean and the defects check. Moving furniture in during carpentry or painting risks damage, and fixing defects can add days. Once your contractor confirms the handover date, leave a small buffer before moving day.

Sources
About this guide

Practical guidance for planning a home job in Singapore. Company prices come from the HomezyPro directory, each linked to its source; rules and safety points link to the agency or manufacturer that sets them. This is not a site inspection, a quote or professional advice for your home.

How HomezyPro works

YOUR NEXT STEP

Find the right team for your home.

Compare services, published prices and sourced reviews. Contact the company directly to confirm your job and availability.

Explore handyman companies