HDB kitchen renovation rules at a glance

The kitchen renovation rules HDB publishes cover five areas: floor finishes, waterproofing, the sink, gas pipes and wiring. Floor finishes and waterproofing sit in its building works guidelines. The sink and gas pipes sit in its plumbing and gas guidelines. Power points and wiring sit in its electrical works guidelines. The table sums up the key points.

Kitchen rules by item
ItemRule
Floor finishesReplacement needs a permit; total finishes and screed 50mm or less
WaterproofingPre-packed waterproofing screed in kitchens before new floor finishes
SinkReplacement has no special conditions; repositioning must not tamper with the structural slab
Gas pipesAltered only by City Energy or an LGSW
WiringNo embedding of wiring

Use the table as a checklist when you brief your contractor. For each item in your plan, ask whether it needs a permit, who will apply for it and which trade will do the work. The sections below explain each rule and link to the official page that states it.

Floor and wall finishes

Replacing floor finishes needs a permit, and the total thickness of floor finishes and screed must not exceed 50mm. In kitchens, pre-packed waterproofing screed must go down before new floor finishes are laid. Both rules come from HDB's building works guidelines.

HDB says an overlay of new floor tiles with adhesive needs no permit, as long as there is one existing layer, the new layer is 13mm or less, the floor trap is left untouched and there is no backflow (HDB building works guidelines).

For how a permit application works, see our guide to the HDB renovation permit. For overlay and thickness details, see HDB floor tile rules.

On the walls, plan any new cable runs before tiling. HDB does not allow new wiring to be embedded in walls or plaster, so new wiring runs in surface trunking, above a false ceiling or behind carpentry (HDB electrical works guidelines).

Sink and plumbing

HDB says sink replacement has no special conditions. If you want to reposition the sink, the work must not tamper with the structural slab (HDB plumbing and gas guidelines). Before you commit to a new layout, ask your contractor how the pipes will reach the new position without touching the slab.

Who does the work matters too. PUB lists installing or replacing a washbasin or sink and its bottle trap as simple plumbing work that a handyman may do. Other water service and sanitary plumbing works, such as moving pipes for a new sink position, need a PUB Licensed Plumber (PUB Plumbing Works).

For the wider set of rules, read our guide to HDB plumbing renovation rules. If the sink is staying where it is, the kitchen sink replacement guide covers the swap.

Gas and electrical points

Fix the positions of the hob, oven and cooker hood first, since the gas and power points follow them.

HDB says gas pipes may only be altered by City Energy or an LGSW, and gas pipes must not be embedded in common partition walls (HDB plumbing and gas guidelines).

For power, HDB says embedding wiring is not allowed. Additional 13A power points need no HDB permit, but SP Services Form CS/5H must be submitted for testing of the new wiring. A 15A power point or 20A isolator in a flat with a 30A main switch needs a permit (HDB electrical works guidelines).

Electrical work at home, including installing, repairing or modifying wiring and adding, extending or replacing power points, should be carried out or supervised by an Energy Market Authority (EMA) Licensed Electrical Worker (LEW). EMA says electrical work in an HDB flat needs a Licensed Electrician, the class of LEW approved for loads of up to 45kVA. See EMA's page on engaging licensed workers before you hire.

Switching from a gas hob to induction? Read our guide to induction stove installation before you finalise the counter layout.

NEXT STEP

Not sure which trade you need? Answer a few questions and see the matching companies with their published prices and sources.

Find the right service

Plan the order of work

This order is practical advice, not any agency's rule. It spares later trades from breaking finished work to reach pipes or wiring.

  1. Layout and points. Fix the positions of the sink, hob, oven, cooker hood and power points, and check whether any works need an HDB kitchen permit.
  2. Hacking and pipes. Remove old finishes, then have water, sanitary and gas pipes adjusted by the right licensed trades.
  3. Wiring. Run new wiring in surface trunking, above a false ceiling or behind carpentry, and have the new points tested.
  4. Waterproofing and tiling. Lay the waterproofing screed first, then the floor and wall tiles.
  5. Cabinets. Install the cabinets, counter and sink once the tiles are done.
  6. Appliances. Connect the hob, oven, cooker hood and other appliances last.

Questions

Can I move the kitchen sink to the island?

Only if the pipes can reach it without tampering with the structural slab, which HDB does not allow when a sink is repositioned (HDB plumbing and gas guidelines). In practice, the water and waste pipes need a route and enough slope to drain, which often limits how far a sink can move. Ask your contractor to check this before you design around an island.

Can I add power points along the kitchen counter?

Yes, through an LEW. Additional 13A power points need no HDB permit, but SP Services Form CS/5H must be submitted for testing of the new wiring. HDB also says wiring must not be embedded in reinforced concrete slabs, beams or columns (HDB electrical works guidelines), so plan the runs in trunking or behind the cabinets.

Is kitchen waterproofing different from bathroom waterproofing?

It has its own rule. HDB asks for pre-packed waterproofing screed in kitchens before new floor finishes are laid (HDB building works guidelines). Ask your contractor to list the kitchen waterproofing as a separate step in the quotation and to complete it before tiling starts.

Can I install a built-in oven in an HDB kitchen?

Yes, as long as the right trade handles its gas or power supply. HDB says a gas oven follows City Energy's requirements, and gas pipes may only be altered by City Energy or an LGSW (HDB plumbing and gas guidelines). An electric oven needs a suitable point installed by an LEW (EMA's page on engaging licensed workers).

Can I put the washing machine in the kitchen?

Yes, if the spot has a water point and a drain the machine can use. Check both before you plan cabinets around it, and leave space to reach the tap and hose. If it needs new water pipes, that is water service work for a PUB Licensed Plumber (PUB Plumbing Works), not a handyman job.

Who checks the work after the renovation?

New wiring is tested through SP Services, and you check the rest. For new 13A points, SP Services Form CS/5H must be submitted for testing of the new wiring, which your LEW can arrange (HDB electrical works guidelines). For everything else, make a snag list with your contractor covering tiles, sealant, drainage, cabinets and the cooker hood.

Sources
About this guide

Practical guidance for planning a home job in Singapore. Company prices come from the HomezyPro directory, each linked to its source; rules and safety points link to the agency or manufacturer that sets them. This is not a site inspection, a quote or professional advice for your home.

How HomezyPro works

YOUR NEXT STEP

Find the right team for your home.

Compare services, published prices and sourced reviews. Contact the company directly to confirm your job and availability.

Explore handyman companies